Friday 15 October 2010

Footings

The footings are nearly finished, we have large piles of soil now.
We now have to have the building inspector to come and look at them. Then we can fill them with concrete.
Although the concrete has to have 3 days notice and I would like to get it ordered for next week but we need to know when the inspector is coming first.
We have been to Inverness and hired a small compactor (wacker plate) which is to use on the footings before we fill them with concrete.
We also need to order the blocks, sand, gravel, hardcore for the foundations, it's going to be quite busy onsite for the next couple of weeks, at last.
Photos will be posted more frequently, I hope :-)

No comments: