Friday 20 August 2010

Progress

David has dug out the driveway, laid taram matting and then spread the hardcore, so we now have a driveway that delivery people can use.
Iain has finished wiring the barn, installed water to the barn and connected the water tank.
We have a signed wayleave........So now we wait for the electric board to come and dig a trench and get us all connected. Then Iain can turn the barn on, and we can have freezer, tumble drier, an extra fridge and possibly a washing machine.
The nice building warrant man is on holiday for 2 weeks, so there will be no progress on that for at least a fortnight, but we can start sourcing all the building supplies we need for the foundations.
So progress has been made but no building warrant yet!